Early Monday morning, the hefty Vulcan rocket streaked into orbit for the first time, nailing its performance targets and delivering a substantial success to United Launch Alliance on the vehicle’s first test flight.
Unfortunately for the mission’s primary customer, Astrobotic, there was subsequently an issue with the lunar lander’s propulsion system. However, Astrobotic was quick to clear Vulcan of any blame, saying the payload was delivered into the planned lunar trajectory without issue. “There is no indication that the propulsion anomaly occurred as a result of the launch,” Astrobotic said.
Vulcan’s debut was much-anticipated in the US launch community because the rocket provides a potentially viable competitor to the Falcon 9 and Falcon Heavy rockets flown by SpaceX. The US Space Force, in particular, has been waiting on Vulcan to fly dozens of payloads into orbit.
So now that Vulcan has flown once, what’s next?
Next up, Dream Chaser
Just ahead of the launch, two vice presidents with United Launch Alliance, Mark Peller and Gary Wentz, held a teleconference with reporters to address the future of Vulcan.
United Launch Alliance, or ULA, has set aside the next 60 days to review data from the “Cert-1” certification mission that launched on Monday morning, they said. If the data looks good from that flight, the company will move into preparations for the next launch. Wentz said the earliest opportunity to launch this Cert-2 mission is “April-ish.”
The BE-4 rocket engines that will power this Vulcan are in final acceptance testing at Blue Origin’s facilities in West Texas, the officials said. The Vulcan core stage and Centaur upper stage are also in final assembly in ULA’s main factory in Decatur, Alabama. The hardware readiness should be capable of supporting an April launch.
The second Vulcan launch will carry the Dream Chaser spacecraft into orbit for Sierra Space. The winged vehicle will fly a cargo mission that carries supplies to the International Space Station for NASA. After more than a decade of development, Dream Chaser is undergoing final tests. However, there remain some questions about when it will be ready for its debut launch.
The Dream Chaser mission does not have a specific launch date on NASA’s internal schedule, but it shows a potential docking with the International Space Station for 45 days during a period between early April and mid-June. The docking port for the mission will not be needed by other spacecraft this year, so ULA and Sierra Space have some flexibility with the launch date.